.
Add title here
Download
Mega Nav Image
The Social Way Toolkit
Find out more
Add title here
Download
Mega Nav Image
Main Content

Task 8 – Monitor and evaluate

Contents in this section:

CHECK

A monitoring and evaluation framework should be developed to track the effectiveness of each SED project and the SED Plan in total.

Task 8 – Monitor and evaluate

Guidance on monitoring and evaluation (M&E) is included in Section 1. An example of SED monitoring is included in Table 4A.7.

Long-term objectives identified as part of Review and Planning (see Section 2) relate to SED. A monitoring and evaluation framework should be developed to track progress against these long-term objectives.

At the SED project level, M&E should be applied to assess if the SED project is achieving the results as planned and is effective in achieving the expected outcomes and positive impacts.

The SED project ToR should include the M&E framework, defining clearly:

  • Objectives of the SED project.
  • Input targets/indicators: resources expected to be needed, including time, people, finances, information, expertise to deliver activities.
  • Output targets/indicators: direct, measurable results derived from activities, which can be quantitative or qualitative.
  • Outcome targets/indicators: observable changes that have occurred and can be directly linked to the SED project.
  • Impact targets/indicators: estimated longer-term effects of outcomes on households, communities and society which the SED project helped bring about but are the result of a combination of factors, which cannot be directly influenced.

SED project M&E frameworks should be co-ordinated across SED projects where possible. In addition, M&E frameworks of Group-led projects should be leveraged.

Monitoring is an ongoing activity that should be incorporated into everyday SED project work, which also means that it should be resourced for.

Indicators are regularly monitored to assess whether the SED project is implemented according to plan in order to help the project manager quickly identify and solve any issues.

Participatory monitoring is not a mandatory requirement in relation to SED. However, it is good practice and recommended where community trust in the site is low. The CEF could be used as a mechanism to establish and sustain participatory monitoring for SED. This is especially valuable given the collaborative approach required to address SED-related issues. More information about participatory monitoring is included in Governance (see Section 1)

Regular reports summarising the monitoring results for all SED projects should be shared with Group SED/CRD to enable the business to have an overview of projects by SED element, and to enable support to be provided for SED projects early on in case of problems.

Evaluation, in contrast to monitoring, should take place at specific times during the SED project. Baseline research should take place prior or near the start of an SED project to obtain information that allows to define meaningful indicators and targets against which changes, over time, can be tracked and compared. Further evaluations are usually made at intervals of between two and three years and at the end of the SED project. Evaluation can be conducted by the site or by, or in collaboration with, external, independent parties, which may be seen as more objective and hence credible.

In order to assess the efficiency and effectiveness of flagship SED projects and larger expenditures, the Social Return on Investment (SROI) approach can be considered. SROI is an outcomes-based measurement tool that helps understand and quantify the social, environmental and economic value of SED projects. Developed from traditional cost-benefit analysis, SROI is a participative approach that allows to monetise outcomes and impacts so that they can be weighed against project costs. SROI can also be used upfront for developing SED projects by supporting decision-making. See the SROI Tool for more information (see 4A.4 Tools and Guidance Notes)

Multi-year SED and CRD projects should include a mid-term and end-of-project evaluation led by Group SED/CRD. For SED projects that are multi-year or multi-phase, and have a budget exceeding a certain size an external evaluation should be undertaken. Table 4A.6 gives further guidance on this

TABLE 4A.6 Evaluation guidance criteria

Required evaluation type for projects* Total SED project cost SED project cost per annum Project duration Level of risk
External evaluation (interim and end-of-project) > $1.5M > $1M
Interim and end-of-project evaluation $500k – $1.5M $500 and < $1M > 24 months Tackling a risk >20
End of project evaluation only $250k – $500k $250 – $500k >12 and < 24 months >10 and <20
No evaluation < $250k <12 months

* Not programmes

The evaluation process should provide lessons learned that should be used for ongoing SED planning; and, therefore, all evaluations (internal and external) should be shared with Group SED/CRD. Lessons learned may be related to whether:

  • the delivery mechanism was effective;
  • there were any unintended effects;
  • the theory of change was accurate;
  • resources allocated were sufficient;
  • the monitoring and evaluation process, including data collection, was efficient.

TABLE 4A.7 SED Monitoring and Evaluation Framework and Examples

Potential Impact Controls Objective Control owner Timeline Inputs Implementation check Outputs Outcomes Impact

Describe the potential impact

List the controls

What are we trying to achieve?

List function responsible for the control

Date the control should start and be competed

Human and financial resources needed to implement the control

How do we know that the controls are being implemented?

Outputs produced

Changes that have occurred as a result of control ‒ include sources of verification

Value and success in managing the impact ‒ Include sources of verification

Increased income generation in the area of influence

Training for local businesses on participating in local procurement opportunities

Increased local procurement

SED team

Supply Chain

Start date, end date

$ to fund venue hire, transport, logistics and training-material development

1 FTE dedicated to implementing the SED project for 1 year

Training logs show attendance of local business

80% of participants indicate they have achieved the learning objectives of the training

30 stakeholders use the skills they gained to register their business with supply chain

Increasing percentage of local procurement delivered to local businesses

Source: Percentage of local procurement after training is higher than before training

Increase in average household income in targeted area

Source: Baseline data shows that average household income in targeted area is higher after training than before

Increased rates of social ills in the area of influence related to in-migration

Provide funding to local addiction-support centre

The local addiction-support centre to be able to cope with an increase in demand for its services to improve community awareness, prevention, and rehabilitation and aftercare related to substance abuse

SED team

Occupational Health team

Start date, end date

$ to fund clinic

1 FTE managing the SED project

$ transferred to local addiction support clinic

Number of local community members treated for addiction issues

Number of addiction-awareness campaigns launched

Reduction in incidence rate of substance-abuse rates by SED project completion

Source: Baseline data shows decrease in substance-abuse rates

Health indicators for well-being in area of influence improving

Source: Baseline data shows that health indicators for well-being in area of influence improve over time

4A.2 Guidance | Check
4.Impact and risk prevention and management  |  4A Socio-Economic development (SED)  |  4A.2 Guidance  |  Check