.
Add title here
Download
Mega Nav Image
The Social Way Toolkit
Find out more
Add title here
Download
Mega Nav Image
Main Content

4F.2 Guidance overview

Contents in this section:

4F.2 GUIDANCE

The following provides a guide to managing land access, displacement impacts and resettlement projects following the Plan Do Check Act (PDCA) cycle (see Figure 4F. 1). LADAR requires management at both site-level and at resettlement project-level in accordance with the IDM. Figure 4F. 2 shows how the PDCA tasks correspond with the IDM phases and associated investment assurance.

Figure 4F. 1 The PDCA cycle as relevant to LADAR

Tasks 1 to 3 are undertaken at site-level and are the responsibility of the operations team (with inputs from and co-ordination with other Functions, and support from Group, BU and/or external resettlement consultants as required). Task 1 involves the identification of potential future resettlement projects; some sites may require only one resettlement project, but there will be instances where a site will have two or more resettlement projects that need to take place in different areas and at different times in the site’s lifecycle.

Tasks 4 and onwards are undertaken separately for each individual resettlement project; it is possible that the same site may be simultaneously engaged in different tasks for separate resettlement projects. Task 4 (detailed scoping of the resettlement project) up to Task 9 (implementation of the DMP) will be managed by a resettlement project team, with support from the operations team. During Task 9, once households have been relocated and assets compensated or replaced as agreed, the responsibility for the remaining implementation activities and PDCA tasks (Tasks 10 to 13) reverts to the operations team.

Figure 4F. 2 Flow diagram of LADAR PDCA and IDM phases

4F Land Access, displacement and resettlement | 4F.2 Guidance
4.Impact and risk prevention and management  |  4F Land Access, displacement and resettlement  |  4F.2 Guidance